im only looking for someone who understands project management and can do the critical path drawings and calculation

im only looking for someone who understands project management and can do the critical path drawings and calculation

im only looking for someone who understands project management and can do the critical path drawings and calculation

Question Description

Case Study: Risk Management and Evaluation

Nuclear energy is one of the possible alternative energy to meet the increasing energy demand in the world. Unlike coal and gas, nuclear power can be considered as clean from pollution. In this context, the UAE has increased its focus on this energy in order to comply with its vision of being a clean industrial country that sustain environment and people. As the risk manager of a project sponsored by Barakah, you are assigned the role of managing and evaluating risks that might affect the project during the execution phase. The project is scheduled to start from July 2021, it consists of power plant extension that include expanding the power plant building and installing new electrical machines to boost the produced electric power. During a brain storming session, you discovered that the current pandemic, due the COVID-19, could be a triggering event that might lead to the occurrence of several risky events. The following represents data about the project prior to the risk study:

Activity

Description

Immediate Predecessor

Activity Time : T

(in days)

A

Plant specifications study

5

B

environmental impact study

A

6

C

Engineering study

A

8

D

Demolition, remodeling, and dust control

B

12

E

Enter additional electrical machines and equipment

B

20

F

Job-site security

B,C

16

G

On site execution of the building extension

D,E

25

H

On site execution of the machinery implementation

F

35

I

Testing the new building with machines onboard

F

20

J

security control and safety monitoring

G,H,I

14

Table: Power Plant Extension Project – Data

Part I: Risk Management

As the head of the project risk management team, you will perform some of the risk management steps by replying to the following questions:

Questions:

Part II: Risk Assessment

In order to evaluate the possible risk impact on the project completion, you have conducted a research (using the four risk events you already listed in part I) that have led to the following results: If one risk event occurs during any activity then it will delay the activity buy 2 days. Hence, and in order to apply the PERT technique, you will define three time estimates as following:

To: The activity time: T (from the table)

Tm: T + Delay from the occurrence of two risk events

Tp: T + Delay from the occurrence of four risk events

Questions:

Have a similar assignment? "Place an order for your assignment and have exceptional work written by our team of experts, guaranteeing you A results."

Order Solution Now

Our Service Charter


1. Professional & Expert Writers: Eminence Papers only hires the best. Our writers are specially selected and recruited, after which they undergo further training to perfect their skills for specialization purposes. Moreover, our writers are holders of masters and Ph.D. degrees. They have impressive academic records, besides being native English speakers.

2. Top Quality Papers: Our customers are always guaranteed of papers that exceed their expectations. All our writers have +5 years of experience. This implies that all papers are written by individuals who are experts in their fields. In addition, the quality team reviews all the papers before sending them to the customers.

3. Plagiarism-Free Papers: All papers provided by Eminence Papers are written from scratch. Appropriate referencing and citation of key information are followed. Plagiarism checkers are used by the Quality assurance team and our editors just to double-check that there are no instances of plagiarism.

4. Timely Delivery: Time wasted is equivalent to a failed dedication and commitment. Eminence Papers are known for the timely delivery of any pending customer orders. Customers are well informed of the progress of their papers to ensure they keep track of what the writer is providing before the final draft is sent for grading.

5. Affordable Prices: Our prices are fairly structured to fit in all groups. Any customer willing to place their assignments with us can do so at very affordable prices. In addition, our customers enjoy regular discounts and bonuses.

6. 24/7 Customer Support: At Eminence Papers, we have put in place a team of experts who answer all customer inquiries promptly. The best part is the ever-availability of the team. Customers can make inquiries anytime.

We Can Write It for You! Enjoy 20% OFF on This Order. Use Code SAVE20

Stuck with your Assignment?

Enjoy 20% OFF Today
Use code SAVE20